2019_Spring_RFO_Schedule_and_Status
#1
2019 Spring ReFueling Outage (RFO) schedule.  Updated: 20190624
---------------------------------------------------------------

[ Steps - coastdown, Begin RFO, RPV OPEN, Exit RFO, Completed ]

Planned start date | planned days shutdown | unit ID | Notations
=========================================================


01/05/19 | 39 | LA_Waterford_3 | Completed RFO ( 70 / 39 ) | missed planned restart date

02/06/19 | 20 | GA_Hatch_2 | Completed RFO ( 44 / 20 ) | failed restart | ( -2, 0 ) started early 20190204

02/10/19 | 33 | CA_Diablo Canyon_1 | Completed RFO ( 35 / 33 ) | unit closing in 2024/2025

02/18/19 | 35 | IL_LaSalle_2 | Completed RFO ( 20 / 35 ) 20190218 | change ( +12, 0 ) from 20190206
02/22/19 | 22 | MD_Calvert Cliffs_2 | Completed RFO ( 22 / 26 ) | changed ( +4, 0 ) 20190218 (started on 18th)

03/02/19 | 25 | AL_Browns Ferry_2 | Completed RFO ( 39 / 25 ) | missed planned restart date | power uprate
03/02/19 | 28 | NC_Brunswick_2 | Completed RFO ( 28 / 28 ) | failed 1st restart , 2nd restart

03/03/19 | 36 | VA_North Anna_2 | Completed RFO ( 37 / 36 ) | missed planned restart date
03/06/19 | 90 | MI_DC Cook_1 | Completed RFO ( 55 / 90 ) | baffle bolt replacement

03/09/19 | 34 | OH_Perry_1 | Completed RFO ( 27 / 34 ) | Last RFO – Closing in 2021

03/10/19 | 20 | GA_Vogtle_2 | Completed RFO  ( 18 / 20 ) |  failed restart
03/11/19 | 28 | FL_Turkey Point_4 | Completed RFO ( 30 / 28 ) | missed planned restart date
03/12/19 | 30 | NY_Indian Point_3 | Completed RFO ( 29 / 30 ) | Last RFO - closing April 2021.

03/18/19 | 28 | NY_Nine Mile Point_1 | Completed RFO ( 26 / 21 ) | missed planned restart date, failed restart | changed ( -2, +7 ) 20190320
03/18/19 | 20 | IL_Quad Cities_1 | Completed RFO ( 20 / 20 )  | changed (  -9, +4 ) 20190327

03/22/19 | 26 | WI_Point Beach_1 | Completed RFO ( 27 / 26 ) |
03/23/19 | 35 | PA_Susquehanna_2 | Completed RFO ( 29 / 35 ) | Final 699' feed water heater change out a,b,c.
03/23/19 | 31 | NC_McGuire_1 | Completed RFO ( 25 / 31 ) 20190323 | changed ( -4, +2 ) 20190327

03/29/19 | 34 | LA_RiverBend_1 | Completed RFO ( 42 / 34 ) | 2nd restart failed, 1st restart failed | changed ( -1. -1 )
04/01/19 | 42 | MO_Callaway_1 | Completed RFO ( 46 / 42 ) | changed ( -5, 0 )

04/05/19 | 30 | AZ_Palo Verde_1 | Completed RFO ( 33 / 30 ) |
04/05/19 | 28 | AL_Farley_2 | Completed RFO ( 25 / 28 ) | 1st restart failed |


04/07/19 | 40 | TX_Comanche Peak_1 | Completed RFO ( 35 / 40 ) | missed planned RFO start date | stator replacement.  
04/08/19 | 18 | IL_Byron_2 | Completed RFO ( 16 / 18 ) |

04/13/19 | 26 | TN_Watts Bar_2 | Completed RFO ( 33 / 26 ) | 1st restart failed | changed ( 0, -2 )
04/13/19 | 30 | MN_Monticello_1 | Completed RFO ( 30 / 30 ) | Begin RFO () 20190413 | changed ( -2, 0 )

04/15/19 | 20 | PA_Limerick_2 | Completed RFO ( 18 / 20 ) 20190415 | Begin RFO () 20190415 | changed ( -2, -9 )
04/18/19 | 33 | CT_Millstone_3 | Completed RFO ( 33 / 33 ) | Begin RFO () 20190413 | changed ( 0, +1 )

04/26/19 | 28 | NJ_Salem_1 | Completed RFO ( 67 / 28 ) | change ( +14, 0 )  20190412

05/15/19 | 31 | WA_Columbia_2 | Completed RFO ( 35 / 31 ) | changed ( +4, -4 ) 20190511

----------------------------------------------
 