Spring 2018 ReFueling Outage (RFO) schedule for US stations

Updated 20180612

[ Beginning Mar 12 this page will only be updated when a state change occurs. ]
[ The states will be coastdown, begin RFO, RPV open, exit preps, restart, completed ]

Date Start - Unit Designation - Misc message

02/05/2018 GA_Hatch_1 - Completed  ( used 20 of typical 22 )

02/11/2018 CA_DiabloCanyon_2 - Completed  ( used 39 of typical 33 )
02/17/2018 AL_BrownsFerry_3 - @ 92 %  restart ( used 45 of typ 43 )

02/19/2018 MC_CalvertCliffs_1 - Completed ( used 26 of typ 23 )
02/19/2018 IL_LaSalle_1 - Completed ( used 23 of typ 26 )

03/01/2018 Mi_DCCook_2 - @ Complete ( used 59 of typ 90 )
03/03/2018 NC_Brunswick_1 - Completed ( used 32 of typ 28 )
03/03/2018 OH_DavisBesse_1 - Completed ( used 24 of typ 25 )

03/11/2018 VA_NorthAnna_1 - Completed ( used 34 of typ 29 )
03/12/2018 FL_StLucie_1 - Completed ( used 31 of typical 29 )
03/17/2018 SC_Catawba_2 - Completed ( used 30 of typ 25 )

03/19/2018 NY_IndianPoint_2 - Completed ( used 31 of typ 31 )
03/19/2018 IL_QuadCities_2 - Completed ( used 20 of typ 17 )
03/24/2018 TX_South_2 - Completed (used 33 of typ 38 )

03/25/2018 AR_Arkansas_1 - Completed ( used 44 of typ 35 )
03/25/2018 PA_Limerick_1 -  Completed ( used 21 of typ 26 )  
03/31/2018 PA_Susquehanna_1 - Completed ( used 32 of typ 35 )
03/31/2018 KS_WolfCreek_1 - Completed ( used 47 of typ 41 )

04/07/2018 NC_Harris_1 - Completed ( used 33 of typ 25 )
04/07/2018 TN_Sequoyah_1 - Completed ( used 30 of typ 35 )
04/07/2018 AZ_PaloVerde_3 -  Completed ( used 28 of typ 29 )
04/07/2018 MS_GrandGulf_1 - exit preps ( at 66 of typ 50 ) should restart soon

04/08/2018 AL_Farley_1 - Completed ( used 32 of typ 22 )
04/09/2018 IL_Braidwood_1 - Completed ( used 21 of typ 18 )
04/13/2018 NJ_HopeCreek_1 - Completed ( used 27 of typ 22 )
04/14/2018 PA_BeaverValley_1 - Completed ( used 25 of typ 30 )

04/16/2018 NY_NineMilePoint_2 - Completed ( used 27 of typ 22 )
04/21/2018 SC_Oconee_3 - Completed ( used 27 of typ 28 )
04/22/2018 VA_Surry_1 - Completed ( used 40 of typ 25 )
04/30/2018 IL_Clinton_1 -Completed ( used 21 of typ 20 )



[ from tracking numerous RFO sequences and viewing Reactor Status detail the Reactor Pressure Vessel (RPV) head is generally opened on day 5 ( RFOD_005 ) ]
 
Reply
  


Possibly Related Threads...
Thread Author Replies Views Last Post
  Status of Nuclear Power Plants in the United States LWH 7 5,021 09-13-2016, 08:50 AM
Last Post: piajensen

Forum Jump:


Browsing: 1 Guest(s)